Liquidated Damages or Penalty? What Minnesota Courts Actually Measure

August 25, 2026 · David J.S. Madgett · Updated October 1, 2026

Two questions decide most fights over a stipulated-damages clause, and most write-ups of Minnesota law skip both.

The first is when. Everyone recites that the sum must be a reasonable forecast of the harm. A forecast made when? At signing, when the parties were guessing? Or at judgment, when the court can see exactly what the breach cost? Minnesota’s answer isn’t the clean “time of contracting” rule that gets repeated in seminar materials, and the cases that look irreconcilable stop looking that way once you see what the court is really doing.

The second is what happens next. A clause gets struck as a penalty. Does the plaintiff walk out with actual damages, or with nothing? I’ve seen sophisticated people assume each answer. One of them is wrong, and Minnesota has said so since 1901.

The test, and why it starts in your favor

Minnesota’s controlling statement comes from Gorco Construction Co. v. Stein, 256 Minn. 476, 99 N.W.2d 69 (1959) — a fight over two garages worth $1,800. The supreme court there confirmed that this state doesn’t start from suspicion:

Accordingly this court has long regarded provisions for liquidated damages as prima facie valid on the assumption that the parties in naming a liquidated sum intended it to be a fair compensation for an injury caused by a breach of contract and not a penalty for nonperformance.

Gorco, 256 Minn. at 481, 99 N.W.2d at 74. The court then adopted Restatement, Contracts § 339, which supplies the two elements:

(a) the amount so fixed is a reasonable forecast of just compensation for the harm that is caused by the breach, and

(b) the harm that is caused by the breach is one that is incapable or very difficult of accurate estimation.

Id. at 482, 99 N.W.2d at 74–75. The court of appeals has restated those two elements in exactly that shape. Bellboy Seafood Corp. v. Nathanson, 410 N.W.2d 349, 352 (Minn. Ct. App. 1987). And the modern formulation folds the presumption in with the elements: “Although prima facie valid, a liquidated damages provision is enforceable only where damages are not readily ascertainable and where the amount fixed is reasonable in light of the contract as a whole, the nature of the damages contemplated, and the surrounding circumstances.” E.D.S. Construction Co. v. North End Health Center, Inc., 412 N.W.2d 783, 786 (Minn. Ct. App. 1987), review denied (Minn. Nov. 18, 1987).

This law is old, but it isn’t asleep. The supreme court quoted Gorco’s controlling-factor language again in 2018. St. Jude Medical, Inc. v. Carter, 913 N.W.2d 678, 683 (Minn. 2018).

So who has to put in the evidence?

Here I part ways with most of what’s been written on the subject, and here the presumption stops being trivia. “Prima facie valid” sounds like it settles the burden. It doesn’t, and the newest precedential answer in Minnesota runs against your gut.

In Lagoon Partners, LLC v. Silver Cinemas Acquisition Co., No. A23-0194 (Minn. Ct. App. Dec. 11, 2023), a landlord invoked a rent-acceleration clause against a departed theater tenant, and the district court enforced it partly because the tenant hadn’t produced evidence that the accelerated sum was unreasonable. The court of appeals reversed, and put the burden where the tenant said it belonged:

The district court did not cite any legal authority for the proposition that Landmark bore an evidentiary burden with respect to the enforceability of the liquidated-damages clause. To the contrary, the Gorco opinion indicates that Lagoon bore that evidentiary burden. … The Gorco opinion demonstrates that the proponent of a liquidated-damages clause bears the burden of introducing evidence to justify the liquidated-damages clause.

Slip op. at 20. The reasoning comes straight out of Gorco: the supreme court struck that clause because “the record is almost devoid of any evidence” that the stipulated sum bore a reasonable relation to the loss — a failure of the proponent’s proof, not the challenger’s.

Now set that against the case everyone cites for the opposite proposition. In Dean Van Horn Consulting Associates, Inc. v. Wold, the court of appeals approved a trial court’s decision to take evidence on remand because the first trial had ended before the defendant “was allowed to make a record in an attempt to overcome the prima facie validity of the clause.” 395 N.W.2d 405, 408 (Minn. Ct. App. 1986). Both sides get to build that record, the court said, because “liquidated damages clauses must be considered in light of all the circumstances.” Id.

That’s two published court of appeals decisions pointing in different directions on who carries the load. I don’t think they’re flatly irreconcilable. Dean Van Horn is about a challenger’s opportunity to make a record on remand, not about who has to come forward first, and nothing in it says a proponent may rest on the presumption and say nothing. But that’s a lawyer’s reconciliation, and I wouldn’t bet a case on a district court buying it. A Minnesota judge today follows Lagoon Partners: it’s thirty-seven years newer, it’s squarely on the burden question and not on the scope of a remand, and it reasons from what the supreme court actually did in Gorco instead of from the presumption’s label.

So my rule is the same on both sides of the “v.”: build the record as though the burden is mine. Enforcing, I put in affirmative evidence that the harm resisted pricing when the contract was signed and that the number was tied to something real. Attacking, I never rely on the proponent’s silence alone. I prove the damages were always calculable and then put the actual loss in front of the judge. Neither approach is expensive, and each one covers you if the judge reads these two decisions the other way.

Lagoon Partners also draws the Gorco framework from Maslowski v. Prospect Funding Partners LLC, 978 N.W.2d 447, 455 (Minn. Ct. App. 2022), rev’d on other grounds, 994 N.W.2d 293 (Minn. 2023), which supplies the standard of review you’ll want to know before you brief this: enforceability of a liquidated-damages clause is a question of law, reviewed de novo. Slip op. at 9, 12.

The label on the clause is worth nothing

Write “not a penalty” into the contract if it makes your client feel better. It won’t survive contact with a Minnesota judge.

In determining the issue neither the intention of the parties nor their expression of intention is the governing factor. The controlling factor, rather than intent, is whether the amount agreed upon is reasonable or unreasonable in the light of the contract as a whole, the nature of the damages contemplated, and the surrounding circumstances.

Gorco, 256 Minn. at 481–82, 99 N.W.2d at 74. The supreme court said the same in Meuwissen v. H.E. Westerman Lumber Co., 218 Minn. 477, 483, 16 N.W.2d 546, 549 (1944) — designating the sum as liquidated damages “is not controlling or conclusive.” Nor does the label save the party attacking the clause. In Willgohs v. Buerman, 262 Minn. 415, 115 N.W.2d 59 (1962), the contract recited that the $1,000 was “not as a penalty, but as a liquidation damage,” id. at 416, and the court tested it on the merits anyway. It held up, on evidence that the plaintiff had spent $500 to $600 training the defendant and roughly $250 more finding a replacement.

It cuts the other way too. Where the stipulated sum is exceedingly large, the actual damages are readily ascertainable, and the disproportion is plain, courts compel the parties “to litigate their pecuniary difference on a basis of fair compensation; and this, too, without regard to the express language of the contract.” Taylor v. Times Newspaper Co., 83 Minn. 523, 527–28, 86 N.W. 760, 762 (1901). Even an arbitrator’s loose use of the word “penalty” to describe a clause “neither controls, nor permits an inference that the arbitrator exceeded his power.” E.D.S., 412 N.W.2d at 786.

Which moment does the court measure from?

This is where I part ways with the standard summary. Minnesota isn’t a pure time-of-contracting jurisdiction, and saying it is will get a brief in trouble.

The forward-looking anchor is real. Reasonableness is judged against “the language of the contract itself and the facts and circumstances under which it was made.” Schutt Realty Co. v. Mullowney, 215 Minn. 340, 346, 10 N.W.2d 273, 276 (1943). The same opinion describes the exercise as “the reasonableness of forecasting the future in the light of the present.” Id. at 347. The word the Restatement uses — forecast — only makes sense looking forward. Litigants have built their records that way, offering evidence “concerning the speculative nature of damages as of the time the contract was executed.” Dean Van Horn Consulting Associates, Inc. v. Wold, 367 N.W.2d 556, 559 (Minn. Ct. App. 1985).

Now, what that does and does NOT mean. It doesn’t mean hindsight is inadmissible. Minnesota’s rule on after-the-fact evidence is stated exactly, and it’s been on the books for over a century:

It is not of controlling importance, where the actual damages are doubtful, speculative, and difficult of proof, that the amount stipulated is much larger than the apparent actual injury and loss. … Such fact, however, is always to be considered, but is specially significant only in those cases where the damages may be readily ascertained by the application of definite and certain rules of law.

Taylor, 83 Minn. at 528, 86 N.W. at 762.

Read that twice. It’s the whole structure. What actually happened is always evidence. How much weight it carries depends on the answer to the difficulty element. If the harm was genuinely hard to estimate at signing, a big gap between the stipulated sum and the real loss is close to irrelevant. If the harm was measurable all along, that same gap becomes the case.

Gorco shows how it works. The clause there covered three named items — salesman’s commission, advertising, and committed labor and equipment — all of which the court found “clearly and readily susceptible of definite measurement and proof by ordinary rules.” 256 Minn. at 483, 99 N.W.2d at 75. Having answered the difficulty element against the drafter, the court then relied on the hindsight the drafter couldn’t survive: no commission was ever proved paid, and the seller learned of the cancellation before committing any labor or equipment, so no such expense was incurred. Id. at 483–84, 99 N.W.2d at 75. The clause failed because the damages were measurable and the measured damages were nothing.

That order of operations is why the supreme court can describe Gorco as “holding that a penalty is an agreed-to sum that is greatly disproportionate to the actual damages” — Capistrant v. Lifetouch National School Studios, Inc., 916 N.W.2d 23, 26 n.2 (Minn. 2018) — without contradicting the forecast language. The forecast question looks forward. The disproportion question, once the forecast question goes badly, is measured against what the breach actually cost.

A court of appeals panel ran exactly that sequence in 2023, which is the best confirmation available that this is how the doctrine actually works and not how I’d like it to. Lagoon Partners asked the difficulty question first — “[i]n light of Gorco, we first ask whether Lagoon’s actual damages resulting from Landmark’s breach of the lease are ‘incapable or very difficult of accurate estimation’” — and answered that if they are not, “the liquidated-damages clause in the lease is unenforceable.” Slip op. at 11. Holding that a landlord’s damages on a breached lease are calculable, it struck the clause on that ground alone. Slip op. at 16. Then, having gone on to the forecast question anyway, it measured the stipulated sum against the loss the landlord would really have sustained — one reduced by the duty to mitigate, slip op. at 18, and possibly wiped out altogether, since a landlord who relets at a higher rent can end up with post-termination damages of zero. Slip op. at 19 (citing Provident Mutual Life Insurance Co. v. Tachtronic Instruments, Inc., 394 N.W.2d 161, 165 (Minn. Ct. App. 1986)). Difficulty judged looking forward. Disproportion judged against what the breach really cost.

So when I’m defending a clause, I litigate element two first and hard. I want the record to establish that nobody could have priced this harm in advance. Everything else follows from that. When I’m attacking one, I prove the damages were always calculable, and only then do I put the actual loss in front of the judge.

Can a clause fail because nothing actually went wrong?

No — not on its own, and the rule isn’t unsettled. Minnesota answered it directly:

The rule is well settled that a contract provision for liquidated damages can be enforced without proving actual damages as long as the amount stated is reasonable.

Willgohs, 262 Minn. at 417–18, 115 N.W.2d at 62. The court of appeals has enforced that holding against a trial court that got it backwards, reversing a directed verdict entered because the plaintiff hadn’t proved actual damages: “Since this is a misstatement of the law, the directed verdict was error.” Dean Van Horn, 367 N.W.2d at 559. A plaintiff with a valid clause “need not prove specific amounts of damages suffered.” Id. at 560.

The catch is that Willgohs rests that proposition on a digest, not on a prior decision, and the clause there was upheld on a record showing real out-of-pocket loss. A defendant with a zero-damages record and an ascertainable-harm argument isn’t without a case. But the zero-damages fact alone doesn’t win it. The defendant has to get through element two first, and if the harm was speculative at signing, Taylor says the shortfall is not of controlling importance.

The clause is struck. Who wins?

The plaintiff doesn’t lose the case. It loses the shortcut.

Meuwissen says it in one line, on the way to explaining why judgment on the pleadings would have been improper had the clause been a penalty: “Concededly, the order for judgment was improper if the provision for damages was in the nature of a penalty, since then defendant would be required to prove actual damages.” 218 Minn. at 483, 16 N.W.2d at 549. Taylor said the same thing in 1901 — where the sum is a penalty, courts “require the party asserting injury to prove his actual loss.” 83 Minn. at 527, 86 N.W. at 762. And the Restatement provision Gorco adopted says so on its face: an unenforceable stipulation “does not affect the damages recoverable for the breach.” 256 Minn. at 482, 99 N.W.2d at 74.

Watch what Gorco itself did with the case after striking the clause. It reversed and granted a new trial. 256 Minn. at 484. It didn’t order judgment for the breaching defendant, even though the defendant had won the penalty argument outright.

Here’s the trap. Striking the clause turns the case into an ordinary damages case, and an ordinary damages case takes ordinary proof. In Taylor, the supreme court framed the consequence in exactly those terms: if the sum were a penalty, “the action was properly dismissed, and the order appealed from should be affirmed, because plaintiff failed to prove any actual damages.” 83 Minn. at 526–27.

Read that sentence for what it gives away. The plaintiff in Taylor had proved no actual damages at all, so the entire case turned on one classification ruling. He got out only because the court came out his way on it — holding that the stipulated sum “must be treated as liquidated damages” and reversing the order. 83 Minn. at 529–30. Flip that one answer and there’s nothing left of the case. If you’re enforcing a stipulated-damages clause in Minnesota, you plead and prove actual damages in the alternative. Every time. The clause is a convenience, not a substitute for a damages case, and building the alternative record costs next to nothing compared with staking the whole claim on how a judge classifies a paragraph.

One more consequence you should know: a valid clause is exclusive. “There cannot be both liquidated damages and compensatory damages.” Frank v. Jansen, 303 Minn. 86, 94, 226 N.W.2d 739 (1975). A party can’t collect the stipulated sum and then stack proven losses on top of it. Where the contract doesn’t fit the clause, unjust enrichment and quantum meruit sometimes fill the gap, but they’re not a way around an enforceable liquidated-damages term.

Construction: delay damages by the day

Per-day and per-month delay clauses are the natural home for this doctrine, because delay harm on a real project is exactly the kind of loss that resists advance pricing.

Schutt Realty is the model. The contractor agreed to wreck the old Minneapolis Exposition Building and to forfeit $1,000 for each month of delay. He ran more than four months late. The stipulated exposure was $4,000; the trial court identified roughly $3,000 in identifiable loss and concluded “[t]he discrepancy in the opinion of the Court, is not so great as to make this a penalty.” 215 Minn. at 345. The supreme court affirmed, emphasizing that the value of early possession “was not only extremely difficult but, quite obviously, of the speculative type,” that both sides were competent to contract, and that there was “no suggestion of fraud, overreaching, or mutual mistake.” Id. at 347.

E.D.S. shows the other lever. An AIA owner–contractor agreement on a $293,000 clinic renovation carried a supplementary condition setting $1,000 per day after November 30, 1985. The contractor argued the daily figure was greatly disproportionate to the owner’s real loss. It never got a merits ruling, because the parties had arbitrated: the court held those arguments went “not to the issue of arbitrability but to the merits of the arbitrator’s decision,” and the arbitrator acted within his authority. 412 N.W.2d at 786. A broad arbitration clause can decide the penalty question by deciding who answers it.

For drafting, that means two things. Tie the daily rate to something — the owner’s actual rent, carrying costs, or lost use — the way the E.D.S. clause tied the pre-deadline period to the daily cost of renting the leased space. And don’t itemize the way Gorco’s drafter did. Listing “Salesman’s commissions, advertising, and the committing of labor and equipment to perform the work” — 256 Minn. at 481 — told the court precisely which readily provable items the clause was standing in for. That’s how the drafter lost element two by his own hand. A clause that names its parts invites the court to price them.

Construction carries its own statutory overlay on what a contract may and may not do. I’ve written separately on contract terms Minnesota law voids in construction agreements and on the prompt-payment rules, and I won’t re-derive either here.

Earnest money, and the statute most people miss

A forfeiture-of-deposit clause in a purchase agreement is not automatically a liquidated-damages clause. That’s the holding of Frank v. Jansen, and it surprises people:

[A] provision in a contract of this kind calling for a forfeiture of the downpayment upon a breach of the contract will not of itself establish the fact that it is to be considered as liquidated damages. Whether the parties have stipulated for liquidated damages must be gleaned from the contract and all of the facts pointing to the intention of the parties. Before there can be a finding of liquidated damages, there must be evidence to support a finding that the parties intended the stipulated amount to be in lieu of compensatory damages.

303 Minn. at 93. On a $48,500 sale of a St. Paul residence with a $2,000 “guarantee of good faith,” the printed forfeiture clause had been left blank, and the supreme court reversed the finding that the deposit was liquidated damages.

See how that sits next to Gorco. Intent isn’t the governing factor in deciding whether an admitted liquidated-damages clause is enforceable. Intent is the question in deciding whether you have such a clause at all. Those are two different questions, and running them together is how the cases come to look contradictory.

Costello v. Johnson, 265 Minn. 204, 121 N.W.2d 70 (1963), supplies the drafting lesson. The purchase agreement let the seller “retain the earnest money hereof as a part of his just compensation for such failure, and may declare this contract terminated and proceed for damages, or specific performance against such purchaser.” Id. at 206, 121 N.W.2d at 73, quoted in Frank, 303 Minn. at 92. That election-of-remedies language sank it: the provision “indicates that the parties did not intend to contract with respect to liquidated damages.” Id. at 210, 121 N.W.2d at 75. A clause that reserves the right to sue for more is, by its own terms, not a substitute for damages.

Where the clause isn’t a liquidated-damages term, the ordinary measure governs a buyer’s breach: the difference between the contract price and the market value at the time of the breach, plus expenses reasonably incurred in mitigation, less the downpayment already received. Frank, 303 Minn. at 96.

Now the statute. Minnesota does limit deposit forfeiture on residential deals, and it does it through procedure instead of by capping the number. Minn. Stat. § 559.217 governs cancellation of a purchase agreement for residential real property — one to four families, vacant land included, § 559.217, subd. 1(c) — and it reaches any earnest money contract or exercised option “whether or not the instrument is subject to section 559.21.” § 559.217, subd. 1(b).

A seller who wants the deposit has to run the statute. Where the default is curable, the cancelling party serves a notice giving the other side 15 days to cure, and the statute overrides the contract on this point: the notice “must be given notwithstanding any provisions in the purchase agreement to the contrary.” § 559.217, subd. 3(b). Only after a completed cancellation does the money move — earnest money then “must be distributed to, and become the sole property of, the party completing the cancellation of the purchase agreement.” § 559.217, subd. 7(a).

The counter-move is the part to know. If the party on the receiving end serves its own cancellation notice before the first proceeding finishes, the agreement is deemed cancelled on that second notice, and the deposit fight goes to a judge: “A court shall make a determination of which party is entitled to the earnest money without regard to which party first initiated the cancellation proceeding and may consider the terms of the canceled purchase agreement in making its determination.” § 559.217, subd. 2. That’s where Frank and Gorco get applied. A buyer who answers a cancellation notice with a responsive notice turns an automatic forfeiture into a contested proceeding. A buyer who does nothing for 15 days loses the money without ever reaching the doctrine. Suspension proceedings run through § 559.211, and the court may award filing fees, attorney fees, and service costs to the prevailing party “in an amount not to exceed $3,000.” § 559.217, subd. 6.

Goods contracts run on a different rule

Sales of goods are governed by Minnesota’s Article 2 provision, and its text isn’t the common-law test:

Damages for breach by either party may be liquidated in the agreement but only at an amount which is reasonable in the light of the anticipated or actual harm caused by the breach, the difficulties of proof of loss, and the inconvenience or nonfeasibility of otherwise obtaining an adequate remedy. A term fixing unreasonably large liquidated damages is void as a penalty.

Minn. Stat. § 336.2-718(1). Three differences matter in practice.

Common law (Gorco) § 336.2-718(1)
Timing Forecast judged on circumstances at contracting; actual loss “always to be considered” but weighted by difficulty (Taylor) “Anticipated or actual harm” — hindsight is authorized by the text, not merely admitted
Difficulty of estimation An element; the clause fails without it One of three listed factors, alongside difficulty of proof and inadequacy of other remedies
Effect of failure Clause unenforceable; claimant proves actual damages “[V]oid as a penalty” — same practical result

There’s a fourth wrinkle with no common-law counterpart. Where a seller justifiably withholds goods on the buyer’s breach and there’s no valid liquidated-damages term, the buyer gets restitution of its payments above a statutory floor: “20 percent of the value of the total performance for which the buyer is obligated under the contract or $500, whichever is smaller.” § 336.2-718(2)(b). The seller’s offsets for other Article 2 damages and for benefits the buyer received are preserved by subsection (3). So a deposit forfeiture on a goods contract is capped by statute in a way a real-estate deposit isn’t. Minnesota keeps the pre-2003 uniform text of this section; its history line runs 1965 c 811 and 1986 c 444. The Article 2 warranty framework sits alongside it.

Not every harsh clause is a penalty clause

The gate cases keep drawing this boundary, and it cuts against the instinct to call anything punitive a penalty.

In Capistrant, an employee stood to lose a residual commission — a forfeiture the court of appeals had put at “potentially $2.6 million” — for failing to return company property immediately. 916 N.W.2d at 26. The supreme court wouldn’t analyze it as a penalty at all:

This case is not about liquidated damages because Lifetouch does not contend that the residual commission amount forfeited by Capistrant’s breach accurately represents the damages caused by Capistrant’s failure to return its property. The liquidated-damages or penalty analysis therefore is not applicable to the forfeiture clause at issue in this case.

916 N.W.2d at 26 n.2. What triggers the doctrine is the enforcing party’s own characterization. A clause is a liquidated-damages clause when the party invoking it says the number stands in for its loss. A clause that simply extinguishes a payment obligation is a forfeiture, and forfeitures are policed by a different body of law — disproportionate forfeiture under Restatement (Second) of Contracts § 229, and, where a restrictive covenant is involved, restraint-of-trade review. Id. at 28–29. Minnesota disfavors forfeitures generally, and “those claiming them must show that the equities are on their side.” Harris v. Bolin, 310 Minn. 391, 393, 247 N.W.2d 600, 602 (1976). Harris voided a profit-sharing forfeiture because it was “not limited as to time, harm to the employer, or geographical area.” Id. at 395, 247 N.W.2d at 603.

In practice, when the other side’s clause forfeits something already earned, the penalty argument may be the weaker of the two available attacks. Plead the forfeiture doctrine alongside it.

Consumer contracts are a further carve-out, and I won’t re-derive them here — the piece on terms Minnesota law will not enforce covers that ground. One statutory example shows the pattern: residential late fees are capped at eight percent of the overdue rent payment, and the legislature expressly took them out of this doctrine — “Any late fee charged or collected is not considered to be either interest or liquidated damages.” Minn. Stat. § 504B.177(a). Where the common-law test still applies to a fee, it applies with teeth. The court of appeals held a public-housing late fee equal to half the tenant’s monthly rent unreasonable under Gorco’s controlling-factor standard. Housing & Redevelopment Authority of Duluth v. Lee, 832 N.W.2d 868, 879 (Minn. Ct. App. 2013).

What I do with one of these clauses

Drafting, I write the recital that matters — a specific, factual statement of why the harm resists advance pricing — and I keep the number tied to a category of loss, not an itemized list of provable expenses. I never put an election-of-remedies sentence in the same paragraph, because Costello says that sentence destroys the clause I just wrote.

Enforcing, I plead actual damages in the alternative and I build that record at trial. The Taylor plaintiff came within one classification ruling of walking out with nothing, and under Lagoon Partners the evidence justifying the clause is mine to produce in the first place. The same record does both jobs.

Attacking, I put element two first. If I can show the harm was always calculable by ordinary rules, the presumption of validity stops doing any work and the actual-loss evidence becomes decisive. I also make the proponent’s failure of proof an argument in its own right, because Lagoon Partners says the burden of justifying the number is his — but I never make it my only argument, because Dean Van Horn is still on the books and a judge may read the presumption the other way. If element two goes against me, the gap between the stipulated sum and the real loss won’t carry the day by itself, and I look instead at whether the clause is a forfeiture, a restraint of trade, or simply not a liquidated-damages clause at all.

The doctrine rests on a remarkably small body of Minnesota law — a handful of supreme court decisions, most of them decades old, and a thin layer of court of appeals cases applying them, the newest of which moved the burden. That’s an opportunity, not a problem. The cases are short and readable, and the party that’s actually read them usually knows more about the clause than the party that drafted it.


Madgett Law, LLC litigates and drafts commercial contracts across Minnesota, including construction agreements with delay-damages provisions, purchase agreements and earnest-money disputes, employment and restrictive-covenant terms, and supply contracts governed by Article 2. We handle both sides of these fights — enforcing stipulated-damages clauses and attacking them. To talk through a clause in your contract, send us a message.

Sources: Gorco Construction Co. v. Stein, 256 Minn. 476, 99 N.W.2d 69 (1959) — 256 Minn. at 481 (prima facie validity; label not controlling), 481–82 (controlling factor), 482 (Restatement, Contracts § 339 elements; unenforceable stipulation does not affect damages recoverable), 483 (susceptible of definite measurement; itemized elements readily provable), 483–84 (no commission proved, no labor committed), 484 (reversed and new trial granted). Meuwissen v. H.E. Westerman Lumber Co., 218 Minn. 477, 16 N.W.2d 546 (1944) — 218 Minn. at 483 (designation not controlling or conclusive; penalty means the claimant must prove actual damages). Taylor v. Times Newspaper Co., 83 Minn. 523, 86 N.W. 760 (1901) — 83 Minn. at 526–27 (dismissal where no actual damages proved), 527 (penalty puts the injured party to proof of actual loss), 527–28 (disproportion litigated without regard to contract language), 528 (actual loss always to be considered, specially significant only where damages readily ascertainable), 529–30 (stipulated sum held to be liquidated damages; order reversed). Schutt Realty Co. v. Mullowney, 215 Minn. 340, 10 N.W.2d 273 (1943) — 215 Minn. at 345 (trial court’s discrepancy finding), 346 (facts and circumstances under which the contract was made), 347 (forecasting the future in the light of the present; no fraud, overreaching, or mutual mistake). Willgohs v. Buerman, 262 Minn. 415, 115 N.W.2d 59 (1962) — 262 Minn. at 416 (“not as a penalty” recital), 417–18 (enforceable without proving actual damages if reasonable). Frank v. Jansen, 303 Minn. 86, 226 N.W.2d 739 (1975) — 303 Minn. at 93 (deposit forfeiture not liquidated damages absent intent), 94 (no double recovery), 96 (measure of damages on buyer’s breach). Costello v. Johnson, 265 Minn. 204, 121 N.W.2d 70 (1963) — 265 Minn. at 206 (contract language, quoted verbatim at Frank, 303 Minn. at 92), 210 (election-of-remedies language defeats liquidated-damages construction). Harris v. Bolin, 310 Minn. 391, 247 N.W.2d 600 (1976) — 310 Minn. at 393 (equities on the side of one claiming forfeiture), 395 (overbroad forfeiture as restraint of trade). Dean Van Horn Consulting Associates, Inc. v. Wold, 367 N.W.2d 556 (Minn. Ct. App. 1985) — at 559 (evidence of speculative damages as of execution; directed verdict on failure to prove actual damages was error), 560 (no need to prove specific amounts). Dean Van Horn Consulting Associates, Inc. v. Wold, 395 N.W.2d 405 (Minn. Ct. App. 1986) — at 408 (challenger’s opportunity to make a record against prima facie validity; all the circumstances). Lagoon Partners, LLC v. Silver Cinemas Acquisition Co., No. A23-0194 (Minn. Ct. App. Dec. 11, 2023) (published) — slip op. at 2 (holding, from the opinion body rather than the syllabus), 9 (applicable law; Maslowski), 11 (difficulty element asked first), 12 (enforceability a question of law, reviewed de novo, citing Maslowski), 16 (damages calculable; clause unenforceable), 18 (clause not a reasonable forecast because it ignores the duty to mitigate), 19 (citing Provident Mutual Life Insurance Co. v. Tachtronic Instruments, Inc., 394 N.W.2d 161, 165 (Minn. Ct. App. 1986), where post-termination damages were zero), 20 (the proponent bears the burden of introducing evidence to justify the clause). Slip opinion at mn.gov/law-library-stat/archive/ctappub/2023/. Maslowski v. Prospect Funding Partners LLC, 978 N.W.2d 447, 455 (Minn. Ct. App. 2022), rev’d on other grounds, 994 N.W.2d 293 (Minn. 2023) — at 455 (enforceability of a liquidated-damages clause is a question of law, reviewed de novo). Bellboy Seafood Corp. v. Nathanson, 410 N.W.2d 349 (Minn. Ct. App. 1987) — at 352 (two-element test). E.D.S. Construction Co. v. North End Health Center, Inc., 412 N.W.2d 783 (Minn. Ct. App. 1987), review denied (Minn. Nov. 18, 1987) — at 786 (modern formulation; liquidated damages recoverable only by contract; arbitrator’s “penalty” label not controlling; AIA $1,000-per-day clause). Housing & Redevelopment Authority of Duluth v. Lee, 832 N.W.2d 868 (Minn. Ct. App. 2013) — at 879 (late fee of half the monthly rent unreasonable under Gorco). St. Jude Medical, Inc. v. Carter, 913 N.W.2d 678 (Minn. 2018) — at 683 (reaffirming Gorco’s controlling-factor statement). Capistrant v. Lifetouch National School Studios, Inc., 916 N.W.2d 23 (Minn. 2018) — at 26 (court of appeals’ “potentially $2.6 million” forfeiture figure, as recited by the supreme court), 26 n.2 (liquidated-damages analysis inapplicable to a forfeiture clause; Gorco described as disproportion to actual damages), 28–29 (Restatement (Second) of Contracts § 229 two-prong analysis). Minn. Stat. § 336.2-718 — subd. (1) (anticipated or actual harm; void as a penalty), (2)(b) (20 percent or $500 restitution floor), (3) (seller’s offsets). Minn. Stat. § 559.217 — subd. 1(b)–(c) (definitions), subd. 2 (responsive notice; court determines entitlement to earnest money), subd. 3(b) (notice required notwithstanding contrary contract terms), subd. 6 (fees not to exceed $3,000), subd. 7(a) (distribution of earnest money on completed cancellation). Minn. Stat. § 504B.177(a) (late fee capped at eight percent; not interest or liquidated damages). This article is general legal information about Minnesota law. It is not legal advice, it does not create an attorney–client relationship, and no particular outcome is promised or implied.

Get new guides by email

Plain-English guides to Minnesota law, sent when a new one is written. No schedule, nothing for sale.

Used only to send these guides. Unsubscribe from any email. This is attorney advertising — subscribing does not create an attorney–client relationship.

← All news & articles