You Cannot Lien a Public Project in Minnesota — Here Is What You Do Instead

August 22, 2026 · David J.S. Madgett

A subcontractor calls me with $80,000 in unpaid work on a school addition, and the first thing out of his mouth is that he needs to record a mechanic’s lien before his 120 days run. He is half right. He has a 120-day clock. It is just attached to the wrong instrument. There is no mechanic’s lien on a school, a courthouse, a county road, or anything else a public body owns in Minnesota. What he has instead is a claim on the general contractor’s payment bond under the Public Contractors’ Performance and Payment Bond Act, Minn. Stat. §§ 574.26–.32 — and the bond claim runs on its own calendar, with its own service rules, its own sworn notice form, and a one-year deadline to sue that forgives nothing.

The bond is not a consolation prize. It is usually a better remedy than a lien: the security is a surety company’s balance sheet rather than a parcel of dirt, and the act authorizes an award of attorneys’ fees to a successful claimant. But it is unforgiving about procedure, and the procedure is where subcontractors lose these claims.

Why there is no lien on public work

Minnesota’s mechanic’s lien statute gives an unpaid contributor a lien on the improvement and the land under it — on private projects. The courts settled more than a century ago that the lien remedy does not reach public property, and the Supreme Court said so while explaining what the bond act is for:

The purpose of this statute was the protection of laborers and materialmen performing labor or furnishing material for the execution of a public work to which the mechanic’s lien statute does not apply.Wilcox Lumber Co. v. School District No. 268, 103 Minn. 43, 45, 114 N.W. 262, 263 (1907).

The history explains the structure. Before the legislature acted, a public body that voluntarily took a bond for the benefit of unpaid subcontractors accomplished nothing: in Breen v. Kelly, 45 Minn. 352 (1891), the court held that a county had no power to take a bond for the security of third persons absent express statutory authority, and that such a bond, “though voluntarily executed, is void.” The legislature responded by mandating the bond and giving unpaid subs and suppliers a direct right of action on it. The bond, in other words, is the statutory substitute for the lien you cannot have. And because it substitutes for the lien laws, the courts construe it the same generous way — “a bond of this character must be given a liberal construction in favor of those who make contribution to the public improvement.” Guaranteed Gravel & Sand Co. v. Aetna Casualty & Surety Co., 174 Minn. 366, 374, 219 N.W. 546 (1928).

Liberal construction of coverage, though, has never meant liberal construction of deadlines. Keep the two ideas separate.

Which contracts must be bonded

Section 574.26, subdivision 2, does not merely require the bonds — it voids the contract without them. Except for contracts below the threshold in Minn. Stat. § 471.345, subdivision 3 — currently $175,000 — and the narrow exceptions in §§ 574.263 and 574.264 for certain natural-resource projects, a contract with a public body for public work

is not valid unless the contractor gives (1) a performance bond to the public body with whom the contractor entered into the contract, for the use and benefit of the public body to complete the contract according to its terms, and conditioned on saving the public body harmless from all costs and charges that may accrue on account of completing the specified work, and (2) a payment bond for the use and benefit of all persons furnishing labor and materials engaged under, or to perform the contract, conditioned for the payment, as they become due, of all just claims for the labor and materials.” Minn. Stat. § 574.26, subd. 2.

“Public body” means “the state, municipal corporation, school district, or other public board or body.” Minn. Stat. § 574.26, subd. 1(b)(1). The penalty of each bond must be not less than the contract price (for state contracts let by the commissioner of administration or the Department of Transportation, the commissioner may fix the penalty at no less than three-quarters of the contract price), and if the price later increases, the public body may demand additional bonds — with work stopping if they do not appear within ten days. Minn. Stat. § 574.26, subd. 3. Subdivision 1a carves out a short list of exemptions: manufacturers producing at least 100 public transit buses a year, certain Department of Transportation projects at the commissioner’s discretion, and routine road maintenance — “snow removal, ice removal, grading, or other similar routine road maintenance on town roads.”

Two bonds, two jobs. The performance bond protects the public body; if the contractor walks off the job, the owner looks to it. The payment bond is yours. Everything below is about the payment bond.

Who can claim on the payment bond

The bond runs to “all persons furnishing labor and materials engaged under, or to perform the contract.” Minn. Stat. § 574.26, subd. 2. The statutory definition of “labor and materials” is broader than most people expect: “work, skill, tools, machinery, materials, insurance premiums, equipment or supplies, or taxes incurred under section 290.92, chapter 268, or 297A.” Minn. Stat. § 574.26, subd. 1(b)(2). In Guaranteed Gravel itself, one of the consolidated claimants was a workers’ compensation insurer collecting $1,000 in premiums. First-tier subcontractors and their suppliers are the core cases; the further a claimant sits from the prime contract, the harder it must work to show its contribution was furnished “under, or to perform” that contract. That statutory phrase — not a tier label — is what controls, and I read the furnishing-of-coverage cases, running back to Fay v. Bankers Surety Co., 125 Minn. 211, 146 N.W. 359 (1914) (coal burned generating power for the work covered; horse feed and provisions not), to draw the line at contributions reasonably incident to performing the contract, as against goods merely sold to someone who happened to be working on it.

One more feature worth the price of admission: “[r]easonable attorneys’ fees, costs, and disbursements may be awarded in an action to enforce claims under the act if the action is successfully maintained or successfully appealed.” Minn. Stat. § 574.26, subd. 2. Mechanic’s lien claimants get a version of this on the private side; bond claimants get it here, and it changes settlement dynamics on five-figure claims that would otherwise cost more to litigate than they are worth.

The two clocks: 120 days to give notice, one year to sue

Section 574.31, subdivision 2, is where these claims die. Two deadlines, both measured from the claimant’s own last furnishing of labor and materials — not from project completion, not from the invoice date, not from when the general stopped returning calls.

First clock — the 120-day notice. No action lies on the payment bond unless,

“within 120 days after completion, delivery, or provision by the person of its last item of labor and materials, for the public work, the person serves written notice of claim under the payment bond personally or by certified mail upon the surety that issued the bond and the contractor on whose behalf the bond was issued at their addresses as stated in the bond.” Minn. Stat. § 574.31, subd. 2(a).

Note the conjunction. Service on the surety alone is not service; the statute requires both the surety and the contractor, at the addresses stated in the bond. The notice must specify the nature and amount of the claim and the date of the claimant’s last item, and the statute prints a sworn form — notarized, stating that the claim is correct and unpaid — that is “sufficient if it is substantially as follows.” Use the statutory form. I have never seen a reason to improvise on it.

There is one escape hatch: if the contractor failed to comply with § 574.28 by omitting its own address or the surety’s from the bond, no notice is required at all. Minn. Stat. § 574.31, subd. 2(b). Do not plan around the escape hatch. Plan around the 120 days.

Second clock — the one-year suit deadline. An action against the surety

“must be commenced within one year from the date of completion, delivery, or provision by the claimant of its last item of labor and materials for the public work stated in its notice of claim.” Minn. Stat. § 574.31, subd. 2(c).

The year can be extended, but only by the two mechanisms in subdivision 2(d): a written stipulation with the surety executed before the year runs, or a written notice from the claimant extending the deadline by one year, sent by certified mail 90 days before the deadline expires, which the surety fails to oppose by certified-mail objection within 30 days of receipt. If payment is not yet contractually due within the year — retainage on a long project, for instance — the court continues the action rather than dismissing it. And once one claimant sues, any other bond claimant may be admitted to the action on motion; if the bond cannot cover everyone, claims are prorated. Minn. Stat. § 574.31, subd. 2(c).

What if the public body never took a bond?

Then the public body itself is on the hook. Under Minn. Stat. § 574.29, if the public body “fails to get and approve a valid payment bond,” it “is liable to all persons furnishing labor and materials under or to perform the contract for any loss resulting to them from the failure.” The Supreme Court construed the predecessor of this provision in Wilcox Lumber: the public body’s liability reaches the claimant’s actual loss — meaning the claim is against the public body only to the extent the contractor cannot pay, with the contractor’s insolvency as the measure. 103 Minn. at 45–46. And the statute has its own address-based limit: the public body is not liable if the bond fails to list the proper address of the contractor or surety. Minn. Stat. § 574.29.

Section 574.28 also does quiet, useful work for claimants: the bonds must be filed with the public body’s financial officer before work begins, and “[t]he public body must make the payment and performance bonds available for inspection and copying upon request.” That sentence is why the first task on any unpaid public-project claim is a records request, not a demand letter.

Private lien vs. public bond, side by side

Private project — mechanic’s lien Public project — payment bond
Security The improvement and the land The surety’s bond, penalty ≥ contract price
Governing law Minn. Stat. ch. 514 Minn. Stat. §§ 574.26–.32
First deadline Record and serve the lien statement within 120 days after your last item (§ 514.08, subd. 1) Serve sworn notice of claim on surety and contractor within 120 days after your last item (§ 574.31, subd. 2(a))
Suit deadline Enforce within one year after the last item in the recorded lien statement (§ 514.12, subd. 3) Sue the surety within one year of your last item; limited extension mechanics (§ 574.31, subd. 2(c), (d))
Fees See the lien statute’s own mechanics Fees, costs, and disbursements to a successful claimant (§ 574.26, subd. 2)

The symmetry of the two 120-day periods is a genuine convenience — a sub who runs the same internal deadline on every job, public or private, will rarely be caught out. The service targets differ, and that is the detail to systematize. The private-side deadlines and their traps get full treatment in my mechanic’s lien deadlines guide.

The calendar to run from day one

A subcontractor starting a school, road, or municipal job should do five things, in this order:

  1. Day one: request and copy the payment bond from the public body under § 574.28. Confirm it lists addresses for both the contractor and the surety. Calendar nothing from memory; calendar from the bond.
  2. Every month: record the date of your last furnished item as the job progresses. Both clocks run from it, and warranty punch-list visits may or may not restart it — do not litigate that question against your own calendar; treat the last substantive work date as the trigger.
  3. On nonpayment: invoke the prompt-payment machinery — public contracts carry their own interest and pass-through payment obligations, covered in my construction prompt-payment article — while the bond deadlines keep running in the background. A negotiation is not a tolling agreement.
  4. By day 100: serve the statutory sworn notice, certified mail, on the surety and the contractor, at the bond addresses. Serving at day 100 instead of day 119 costs nothing and survives a defective mailing.
  5. By month 10: sue or extend. The 90-day extension notice under § 574.31, subd. 2(d) must go out 90 days before the year runs, so the decision point arrives at roughly month nine, not month twelve.

Claims against the state itself on non-construction theories run through an entirely different channel — see my article on claims against the State of Minnesota. Defect claims flowing the other direction, against contractors, have their own statute of repose, which I cover in the construction defect repose article, and residential work sits inside the license and recovery-fund system described in my contractor recovery fund guide.

Madgett Law, LLC represents subcontractors, suppliers, and contractors in payment disputes on Minnesota public and private construction projects — bond claims, lien claims, prompt-payment claims, and the defense of each. If a public project owes you money and you do not know what your last-item date is, find out today, then call 612-470-6529 or send us a message.

Sources: Minn. Stat. § 574.26, subds. 1(b)(1)–(2) (definitions of “public body” and “labor and materials”), 1a (exemptions), 2 (bond requirement, contract validity, protected persons, attorneys’ fees; $175,000 threshold via Minn. Stat. § 471.345, subd. 3), and 3 (bond penalty ≥ contract price; additional bonds; ten-day stop-work); Minn. Stat. § 574.28 (pre-work filing; addresses; inspection and copying); Minn. Stat. § 574.29 (public body liability for failure to obtain a bond; address limitation); Minn. Stat. § 574.31, subd. 2(a) (120-day sworn notice on surety and contractor), 2(b) (notice excused where § 574.28 addresses omitted), 2(c) (one-year suit deadline; intervention; proration), 2(d) (extension by stipulation or 90-day/30-day certified-mail mechanism); Minn. Stat. §§ 574.263–.264 (natural-resource project exceptions); Minn. Stat. § 514.08, subd. 1 (private lien 120-day statement) and § 514.12, subd. 3 (private lien one-year enforcement), for comparison only; Wilcox Lumber Co. v. School District No. 268, 103 Minn. 43, 45–46, 114 N.W. 262, 263 (1907); Guaranteed Gravel & Sand Co. v. Aetna Casualty & Surety Co., 174 Minn. 366, 374, 219 N.W. 546 (1928); Breen v. Kelly, 45 Minn. 352 (1891); Fay v. Bankers Surety Co., 125 Minn. 211, 146 N.W. 359 (1914). This article is general legal information about Minnesota law, not legal advice. Reading it does not create an attorney–client relationship with Madgett Law, LLC, and no outcome is promised or implied.

Get new guides by email

Plain-English guides to Minnesota law, sent when a new one is written. No schedule, nothing for sale.

Used only to send these guides. Unsubscribe from any email. This is attorney advertising — subscribing does not create an attorney–client relationship.

← All news & articles